We’re urging NFU members to respond to a call for information issued at short notice by the energy regulator, Ofgem.
The regulator is seeking concise feedback on the experiences of small-scale electricity generators in engaging with Distribution Network Operator companies (DNOs), specifically in relation to getting connected to the electricity network. Read its open letter here.
Information on the ‘issues and challenges faced’ will be used by Ofgem in drafting an agenda for a planned ‘Distributed Generation Forum to be held in July 2011. Brief responses need to be sent this week, if at all possible.
The NFU is well aware that obtaining 'distribution grid' electrical connections is often complex, time-consuming and costly for many rural electricity generators. We have been calling upon the government to require Ofgem to use its powers to bring about fairer, faster, cheaper access.
We believe Ofgem needs to review and streamline the electrical connection process, introducing connection incentives and consistency between DNOs. Detailed work is also required to reduce red tape and delays in metering and registration of renewables projects, and to ensure connection costs are set at a consistent, proportionate and nominal level.
Ofgem is also considering hosting a separate workshop for anaerobic digestion (AD) plant operators. Please tell them if this would be particularly useful.
Responses should be sent (this week if possible) to:
Stacy Altman
Distribution Policy
Ofgem
9 Millbank
London SW1P 3GE
stacy.altman@ofgem.gov.uk
Evidence should arrive no later than next Tuesday, 31st May.
- peter cox - 26/05/2011
My email should have said G83 as the G59 is for larger installations
- peter cox - 26/05/2011
We fitted a 9Kw array in early April,installation was straightforward. It was attached to a 3 phase supply with the 3Kw allowance per phase (I believe this is in the process of being increased)for a G59 licence i.e a given right to supply to the Grid. Our biggest problem was in getting the MCS certificate to the electricity company in the 5 days from fitting which is a requirement to get the FiT payment from day one. I understand that payments are made by cheque from a customer reading every three months. We have an LED display in our office and have produced just over 2Mwh and "saved" 1.25 tonnes of CO2.
- Patrick Allen - 26/05/2011
We are in the process of installing a 35kw solarpv system. Our DNO, UK Power Networks took about 3 months to produce the G59 and now are demanding £6500 in order to 're-tap' the transformer. I am informed that this simply requires the power to be turned of and a dial alter in the transformer before it is then turned back on. Sounds as though we are being held to ransome on this one.